Question 5

FIDIC RED BOOK (1999 EDITION)

How many types of formal communications exist in the General Conditions?

 

The answer will be posted in the next blog!

 

Question 4

FIDIC RED BOOK (1999 EDITION)

TRUE or FALSE: “Goods” include the Contractor’s Plant and Temporary Works.

Answer:  True – Sub-Clause 1.1.5.2

Don’t forget, follow or connect with me to gain access to new questions and answers.